Hello Community,
As the Fiat Gateways project is the most important project for us at the moment, we have established a regular call with our partners from Deginner (who is our vendor here) to discuss the project status and share an update with the community.
Here is the first update from 1st June:
Internal project management issues were resolved by the Vendor. New resources were engaged; the project team is stable and works on the code.
Due to the sourcing issues, there is a significant delay in timelines. New project timelines need to be set and new plan created.
Project is stable form the budget perspective.
Deginner works on the internal accounting process to distribute and approve funds with the customer involvement (to improve transparency measures). It will be done using the multi-signature wallet.
More detailed status report is available here: https://dashpay.atlassian.net/wiki/display/OC/Fiat+Gateways
As the Fiat Gateways project is the most important project for us at the moment, we have established a regular call with our partners from Deginner (who is our vendor here) to discuss the project status and share an update with the community.
Here is the first update from 1st June:
Internal project management issues were resolved by the Vendor. New resources were engaged; the project team is stable and works on the code.
Due to the sourcing issues, there is a significant delay in timelines. New project timelines need to be set and new plan created.
Project is stable form the budget perspective.
Deginner works on the internal accounting process to distribute and approve funds with the customer involvement (to improve transparency measures). It will be done using the multi-signature wallet.
More detailed status report is available here: https://dashpay.atlassian.net/wiki/display/OC/Fiat+Gateways